Federal judge says U.S. Dept. of Energy must stop
drilling at nuke dump site in Nevada
September 2007
U.S. Water News Online
LAS VEGAS -- Nevada can shut off water that the
U.S. Department of Energy says it needs for drilling at the
proposed Yucca Mountain nuclear waste repository, a federal
judge has ruled.
The federal government can't ignore state limitations and
continue using water for drilling test bore holes near the
repository site, U.S. District Judge Roger Hunt in Las Vegas
said in a strongly worded order.
"The only argument the DOE makes is that because the site
has been approved ... it has the authority to do whatever it
wishes," Hunt said in his 24-page order. "It has failed to
demonstrate the necessity of its voracious water demands."
Nevada has long complained that the federal government
kept increasing the scope of the drilling and its water
needs -- from about 15 bore holes to 80 and from 300,000
gallons of water to 3.5 million gallons.
Hunt did not decide the merits of the case, filed in
August 2002.
Instead, he denied the federal request for a preliminary
injunction that would hindered the state from restricting
water to the arid site, 90 miles northwest of Las Vegas.
Energy Department spokesman Allen Benson in Las Vegas
declined to comment immediately on the ruling, saying Yucca
Mountain project officials were reviewing the order. Benson
said he didn't know whether drilling had stopped.
Senate Majority Leader Harry Reid, a Democrat who has led
state opposition to the Yucca project, hailed the ruling as
a victory for state rights.
"The federal government will do anything it can to try to
turn Nevada into the nation's nuclear dumping ground, even
if that means ignoring the law and the will of the people
who would be most affected by the dump," Reid said in a
statement. "I am pleased that Judge Hunt upheld Nevada's
right to enforce its water laws."
Marta Adams, a deputy state attorney general, said the
state would seek a contempt of court order if drilling did
not stop.
The judge rejected federal claims that scientists needed
to test areas around the Yucca site to "meet congressional
mandates" and demonstrate the suitability of the site for
entombing 77,000 tons of radioactive waste now being stored
at nuclear reactors in 39 states.
Site characterization tests were supposed to have been
completed before the site was recommended to Congress in
2002, Hunt said.
Hunt also rejected arguments that state officials were
using water as a weapon to delay the project, and that the
Energy Department would suffer irreparable harm if data
collection was delayed.
The government lost $350,000 by paying for idle drill
crews after the state issued a cease-and-desist order on
June 1, Justice Department lawyer Stephen Bartell had
argued. That order was temporarily lifted June 12, but was
reinstated eight days later, after the two sides failed to
agree on conditions for using the water.
The Energy Department once hoped to open the repository
by 2010. But the projected opening date has been pushed back
at least to 2017 by legal challenges, budget issues,
political opposition and scientific controversies.
|